Case Study: Lift Pump System Rebuild Project Overview Issue: Sewage backup into three site buildings Scope: Assess lift station, rebuild if necessary, and test Background Three buildings on the site were experiencing sewage backups in their campus area. The top of the lift station was severely rusted and damaged, and the suction stand pipes had […]
Project Overview Client: Local HOA Office Complex Location: Shreveport La. Issue: Drain on Assembly constantly discharging Scope: Assess assembly, replace if necessary, and Test Background An office building in the downtown area has a Backflow Assembly that continues to discharge water out of the drain/relief. Due to the discharge customers’ water bill has been higher […]
Project Overview Client: Local High School Location: Storer High Issue: Persistent clogging and backing up of floor sinks and floor drains Scope: Camera all grease waste lines and identify problem areas, Jet all horizontal lines, camera when complete Background A local high school cafeteria on the South end of town is experiencing and having recurring […]
Problem: AmerCable has a 45-year-old fire tube Cleaver-Brooks boiler. The boiler had 18 cracked tubes with rapid detrition in the lower section, 9 previous plugged tubes that were failing and a damaged main gas burner. Solution: Storer Services was able to diagnose their problem and quickly provide a reliable solution. We could not plug any […]
Problem: Louisiana Delta Community College wants to reduce the risk of catching COVID-19 on all of its campuses. Outside of their current sanitation measures to reduce COVID-19, they wanted additional measures to get students and faculty safely back on campus. They needed a solution that would kill air-borne pathogens like germs, bacteria, viruses, mold, mildew, […]
Problem: Storer Services received a work order to evaluate the operation of air-conditioning units in the rest area bathrooms which were not cooling properly. The air-conditioning units are an Addison 12.5 ton split system with a heat pump and a RenewAire energy recovery ventilator. Solution: The initial inspection identified several issues. The software and hardware […]
Problem: AmerCable has a 45-year-old fire tube Cleaver-Brooks boiler. The boiler had 18 cracked tubes with rapid detrition in the lower section, 9 previous plugged tubes that were failing and a damaged main gas burner. Solution: Storer Services was able to diagnose their problem and quickly provide a reliable solution. We could not plug any […]
NTCC has been focused on maintaining their HVAC equipment so they get the maximum up-time, efficiency, and maximum life span. To accomplish this, we have invested a significant amount of money into the proper repair of broken equipment, scheduling the conditioning of spaces to align with their usage and the proper preventative maintenance. One of [...]
Problem: Storer Services was contacted by UT Health Science Center in Tyler Texas regarding their (3) 20+ year old 500 Ton Trane Chillers. It was determined by UTHSC that the chillers had reached the end of their usable life and needed to be replaced. Solution: Storer Services developed a construction and verification plan for […]
USDA Cotton Classing Case Study What they do: Each bale of cotton that’s farmed in the U.S. must first be classified before being released to the market. USDA Cotton Classing Services of Rayville, LA classifies all cotton from Louisiana, with additional cotton classing services cotton from Mississippi and Arkansas. The Challenge: Every cotton sample that [...]