Solving Back Flow Drain Discharging Issues/Testing

Solving Back Flow Drain Discharging Issues/Testing

Project Overview Client: Local HOA Office Complex Location: Shreveport La. Issue: Drain on Assembly constantly discharging Scope: Assess assembly, replace if necessary, and Test Background An office building in the downtown area has a Backflow Assembly that continues to discharge water out of the drain/relief. Due to the discharge customers’ water bill has been higher […]

Read more
AmerCable Incorporated

AmerCable Incorporated

Problem: AmerCable has a 45-year-old fire tube Cleaver-Brooks boiler.  The boiler had 18 cracked tubes with rapid detrition in the lower section, 9 previous plugged tubes that were failing and a damaged main gas burner. Solution: Storer Services was able to diagnose their problem and quickly provide a reliable solution. We could not plug any […]

Read more
LDCC UV-C Lights

LDCC UV-C Lights

Problem: Louisiana Delta Community College wants to reduce the risk of catching COVID-19 on all of its campuses. Outside of their current sanitation measures to reduce COVID-19, they wanted additional measures to get students and faculty safely back on campus. They needed a solution that would kill air-borne pathogens like germs, bacteria, viruses, mold, mildew, […]

Read more
LA DOTD

LA DOTD

Problem: Storer Services received a work order to evaluate the operation of air-conditioning units in the rest area bathrooms which were not cooling properly. The air-conditioning units are an Addison 12.5 ton split system with a heat pump and a RenewAire energy recovery ventilator. Solution: The initial inspection identified several issues. The software and hardware […]

Read more
AmerCable Incorporated

AmerCable Incorporated

Problem: AmerCable has a 45-year-old fire tube Cleaver-Brooks boiler.  The boiler had 18 cracked tubes with rapid detrition in the lower section, 9 previous plugged tubes that were failing and a damaged main gas burner. Solution: Storer Services was able to diagnose their problem and quickly provide a reliable solution. We could not plug any […]

Read more
Northeast Texas Community College

Northeast Texas Community College

NTCC has been focused on maintaining their HVAC equipment so they get the maximum up-time, efficiency, and maximum life span.  To accomplish this, we have invested a significant amount of money into the proper repair of broken equipment, scheduling the conditioning of spaces to align with their usage and the proper preventative maintenance.  One of [...]

Read more
UT Health Science Center – Tyler

UT Health Science Center – Tyler

Problem: Storer Services was contacted by UT Health Science Center in Tyler Texas regarding their (3) 20+ year old 500 Ton Trane Chillers. It was determined by UTHSC that the chillers had reached the end of their usable life and needed to be replaced.   Solution: Storer Services developed a construction and verification plan for […]

Read more
USDA Cotton Classing

USDA Cotton Classing

USDA Cotton Classing Case Study What they do: Each bale of cotton that’s farmed in the U.S. must first be classified before being released to the market. USDA Cotton Classing Services of Rayville, LA classifies all cotton from Louisiana, with additional cotton classing services cotton from Mississippi and Arkansas. The Challenge: Every cotton sample that [...]

Read more
Hertz Investment Group

Hertz Investment Group

Problem: The Hertz Investment Group contracted Storer Services in February of 2016 to perform a complete overhaul (CPR) on a 1981 Trane centrifugal “Sidewinder” chiller located in the Capital One building in Lake Charles, LA.  The age of the machine and the obsolete design made this project particularly challenging as many of the required parts [...]

Read more